AEP releases
Aug. 14 transmission events timeline; automated controls prevent spread of
blackouts
COLUMBUS, Ohio, Aug. 22, 2003 - American Electric Power (NYSE:
AEP) today released a timeline of events and conditions detected by automated
controls on its transmission grid Aug. 14 when massive amounts of power were
drawn north from AEPīs grid to loads in the vicinity of Lake Erie immediately
prior to the blackout that affected all or parts of eight states and eastern
Canada.
"This timeline provides details of the rapid escalation of events that impacted
our transmission grid, but we will not get involved in the speculation as to the
cause of the abnormal power flow swings across the grid or theorize about events
occurring outside our system," said Tom Shockley, AEPīs chief operating officer.
"We have provided our data to the North American Electric Reliability Council (NERC)
to be included in its analysis of the blackout. Today we are discussing the data
at a Department of Energy technical hearing and in a conference call with our
state regulators. We also are assisting the investigators as they determine the
cause of the outage.
"Itīs important to note that the load and generation on AEPīs grid were in
balance both before and after the beginning of the blackout. This explains how
we were able to maintain grid stability after our automated controls correctly
reacted to prevent the blackout conditions from cascading through our
seven-state eastern grid and to protect lines and equipment from potentially
extensive damage," Shockley said. "Our transmission system is a $3 billion asset
that includes the worldīs largest network of high-capacity 765-kilovolt (kV)
lines that serve as the backbone of the East Coastīs grid. Itīs a robust,
well-designed system that proved its worth last week."
AEP avoided potential widespread outages when automated control systems on its
transmission equipment detected abnormal operating conditions and "tripped" - or
opened - lines that interconnect with FirstEnergyīs transmission grid to the
north. Lines that tripped are near Canton in northeastern Ohio and Findlay in
northwestern Ohio.
After a line opens or trips, it will either close again and allow power to flow.
Or, if the breaker operates (opens and closes) several times and the abnormal
condition is still sensed by the protection devices, the breaker will lockout,
preventing power flow on the line until it is reset by an operator.
"The data indicates that our automated systems performed as designed," said
Henry Fayne, AEPīs executive vice president - energy delivery. "By quickly
detecting abnormal conditions on the lines and attempting to correct the
conditions, the automated relay protection systems prevented the blackout from
spreading onto AEPīs extensive transmission network and shielded our equipment
from possible substantial damage."
When tripped by the automated control systems, a number of the lines were
carrying power flows well above the summer emergency rating for the lines
because of the massive amounts of power being drawn north from AEPīs system. For
instance, the Canton Central - Cloverdale 138 kV line, with a summer emergency
rating of 197 megavolt-amperes (MVA), was carrying 332 MVA when it tripped. The
East Lima-Fostoria 345 kV line, with a summer emergency rating of 1,383 MVA, was
carrying 2,000 MVA when the automated controls tripped the breaker. If a
facility operates at or above the summer emergency rating the equipment can
suffer thermal damage.
"It is likely that the automated controls tripped some transmission lines
moments before they would have burned down because of extremely high power flows
out of our system," Fayne said. "However, the load and generation on AEPīs grid
were in balance at this time, which helped prevent widespread blackouts in AEPīs
service territories. The size and robust capacity of our grid can handle large
swings and remain stable. During this time, our transmission operators were in
contact with FirstEnergy and PJM, our reliability coordinator, analyzing the
situation as events developed."
AEP had approximately 14,000 of its 5 million customers without power for
several hours on Aug. 14. This localized outage, in an area near Mt. Vernon in
east-central Ohio, occurred at 4:38 p.m. EDT, approximately 27 minutes after the
large blackout began. Indications are that the localized outage is related to
other transmission outages in Northern Ohio. Power to the customers was restored
by 9:15 p.m.
TIMELINE OF EVENTS
Summary of Major AEP Transmission Events
8/14/2003 Blackout - All Times EDT
3:41:33 p.m. South Canton - Star, 345kV Circuit, Line Lockout -
high loading (1,272 MVA with a summer emergency rating of 1,383 MVA) and phase
to ground trip. AEP owns 0.69 miles; FirstEnergy owns 33.42 miles. Star is a
FirstEnergy substation.
3:42:53 p.m. Cloverdale - Torrey 138kV Circuit, Line Lockout -
high loading (354 MVA with a summer emergency rating of 245 MVA). AEP owns 0.28
miles; FirstEnergy owns 6.86 miles. Cloverdale is a FirstEnergy substation.
3:44:12 p.m. East Lima - New Liberty 138kV Circuit, Line
Lockout - high loading (152 MVA with a summer emergency rating of 188 MVA) and
phase to ground trip. AEP owns the entire line.
3:45:33 p.m. Canton Central - Cloverdale 138 kV Circuit, Line
Lockout - high loading (332 MVA with a summer emergency rating of 197 MVA).
Breaker failure operation due to multiple operations of 138kV breaker "A1".
(Breaker had six trip-and-close operations in less than three minutes). This
forces the Canton Central - Tidd 345kV line to temporarily operate to isolate
the faulted 138 kV Breaker "A1". The Canton Central -Tidd 345kV line was
abnormal for 58 seconds before resuming normal operation. AEP owns 0.38 miles of
Canton Central - Cloverdale; FirstEnergy owns 12.20 miles. Cloverdale is a
FirstEnergy substation.
3:51:41 p.m. East Lima - North Findlay 138kV Circuit, Line
Lockout - high loading (200 MVA with a summer emergency rating of 247 MVA) and
phase to ground trip. AEP owns the entire line.
4:05:55 p.m. Dale - West Canton 138kV Circuit, Line Operation -
high loading (estimated load - 329 MVA with a summer emergency rating of 245 MVA).
Line remains open at Dale end. AEP owns 3.57 miles; FirstEnergy owns 12.35
miles. Dale is a FirstEnergy substation.
4:08:58 p.m. Galion - Muskingum River - Ohio Central 345 kV
Circuit, Line Lockout - high loading (1,320 MVA with a summer emergency rating
of 1,281 MVA). AEP owns the entire line. Galion is a FirstEnergy substation.
4:09:06 p.m. East Lima - Fostoria Central 345kV Circuit, Line
trip at 2,000 MVA (summer emergency rating of 1,383 MVA) - high loading. Auto
reclose is delayed by the Synchronizing Check Relay (a snapshot of data at
4:09:22 p.m. from East Limas protective relay showed FirstEnergy and AEP to be
104 degrees out of synchronization). Line closed successfully in 1 minute and 44
seconds. AEP owns the entire line.
4:09:22 p.m. Cloverdale - East Wooster 138kV Circuit, Line
Lockout - high loading (data not available). AEP owns 0.61 miles; FirstEnergy
owns 20.39 miles. Cloverdale is a FirstEnergy substation.
4:10:41 p.m. Fostoria Central - Galion 345kV Circuit, Line
Lockout - high loading (data not available). AEP owns the entire line. Galion is
a FirstEnergy substation.
4:38:02 p.m. Academia - Howard 138kV Circuit - Breaker failure
operation due to multiple operations of 138 kV Breaker "S" (breaker had six trip
and close operations in a short time period - high loading and phase to ground
trip). This caused a total outage to Academia Station interrupting approximately
14,000 AEP customers. AEP owns the entire line.