Connecting a Good Neighbor to the Grid | PowerGrid International

May 22, 2017 | In the News

Connecting a Good Neighbor to the Power Grid:
Electrical Power Studies Important for Wind Power Plants

Published via PowerGrid International

by Dave Mueller

 

 

 

 

 

 

Wind plants require much engineering, and electric power studies are a fundamental part of that engineering effort. These studies ensure safe and reliable operation of the power grid with the wind plant connected. Their objectives are to assess the impact of the wind plant on the transmission grid and determine the rating and sizing for the wind plant equipment. Wind power plant (WPP) studies are classified under two main categories: system interconnection and the balance of plant operation.

System Interconnection Studies

System interconnection studies evaluate the ability of the wind plant to “be a good neighbor” on the transmission grid. These characteristics have become important because in some transmission regions wind power can account for up to 50 percent of the power being delivered to the system. Wind plants must not negatively affect the system’s power quality, and they must actively provide voltage and reactive power support to the grid. Dynamic studies of transmission systems must include electrical models of the wind turbines and power equipment.

Reactive Power Requirements

The wind plant collector system provides reactive power during still (no generation) conditions, because the miles of underground cable contribute charging capacitance to the electrical situation. In locations where “net zero” reactive power capability is required, correctly sized shunt inductors are installed in the substation to cancel this charging capacitance.

During increasing levels of generation, the wind plant collector capacitance becomes less important, but the turbines’ reactive power characteristics and the transformers’ and cables’ reactive losses become dominant. As part of the transmission operator’s large generator interconnection agreement (LGIA), the plant is required to provide (or consume) reactive power to support (or lower) grid voltage. A reactive power study verifies that the plant can provide the reactor power support that is required, or it determines what additional capacitor banks, shunt reactors, or dynamic voltage restorer (DVR) and distribution static synchronous compensator (D-STATCOM) dynamic support may be required.

Harmonics Compliance

The LGIA also requires compliance with the IEEE 519 “Recommended Practice and Requirements for Harmonic Control in Electric Power System.” This standard recommends limits for controlling harmonic voltages and currents on the power system. The goal is to maintain a clean waveform as shown in Figure 1.

FIGURE 1: System Voltages in Normal Condition
FIGURE 1: System Voltages in Normal Condition

At most wind power plants, the harmonics created by the wind turbine converters are small-the current distortion is generally less than 5 percent at full output voltage source-and inverters are used. At a few plants, the inverter controls interact with the grid resonance, causing problems as shown in Figure 2. These problems are generally addressed by modifying the turbine controls to implement “active harmonic damping,” or other countermeasures that will restore the converter’s stability at the grid resonant frequencies.

The IEEE 519 Standards were not originally intended for wind power plants, therefore, the limits are too restrictive and the standards’ applications need some engineering consideration.

FIGURE 2:
FIGURE 2: System Voltages in Resonance Condition

Voltage Fluctuation (Flicker) Evaluation

Electric utilities measure voltage flicker to evaluate voltage variations’ effect on light flicker. They are measured on two-hour (Plt) and 10-minute (Pst) evaluations. In practice, most utilities use the short term 10-minute timescale as their “go to” evaluation. It measures values of Pst < 1.0 pu over all the 10 minute intervals.

Turbines installed at large scale wind plants operate diversely in terms of when they cut-in (begin operation) and generally do not create flicker concerns on large transmission systems. Figure 3 is an example of flicker levels that are below the level of concern. Flicker can be an issue for individual turbines connected to a lower voltage distribution system.

FIGURE 3: Wind Plant Voltage Flicker Measurement (Limit is Pst=1
FIGURE 3: Wind Plant Voltage Flicker Measurement (Limit is Pst=1)

Subsynchronous Resonance Screening

Subsynchronous resonance (SSR) occurs when a series of capacitor compensated transmission lines create a grid resonance that interacts with generator equipment. This potential problem of series compensated lines was initially postulated in a 1937 paper by J.W. Butler, and C. Concordia titled “Analysis of Series Capacitor Application Problems.” The potential was not realized, however, until the 1970s when two large generator shafts failed due to torsional interaction. Then in 2009, ERCOT reported a similar event involving a wind plant.

In the case of the wind plant, system contingencies (lines out) required the wind plant to be radially fed from a series compensated transmission line. The subharmonic (less than 60 Hz) resonances interacted with the wind turbine controls. This phenomenon has been described as subsynchronous control instability (SSCI).

Screening studies evaluate a wind plant’s potential to go into SSCI. The evaluation involves a contingency evaluation of the transmission system or the control loop stability of the wind turbine equipment or a combination of both. Detailed knowledge of the transmission system and the wind turbine control loops are essential for these studies. Figure 4 shows the results of a study in which a line outage caused the wind plant to be radially fed from a series compensated transmission line and when the controls went into unstable operation.

FIGURE 4: Wind Plant Output During Subsynchronous Controls Instability (SSCI
FIGURE 4: Wind Plant Output During Subsynchronous Controls Instability (SSCI)

Power System Model Validation

Power grid transmission operators request wind plant power flow and dynamic response computer models for their studies. They perform dynamic simulations to evaluate system response to faults, lines tripping, generator tripping and other power system transient events to evaluate what the system needs to remain stable and avoid wide-scale blackouts. These studies are usually done using either the Siemens PSS®E (generally eastern U.S. utilities) or GE PSLF (generally western U.S. utilities) software.

Large renewable generating facilities-especially wind and solar-have been full-fledged citizens of the bulk electric system (BES) in the U.S. for almost two decades. The process toward achieving this status has been steady but full of challenges. The initial hurdles of characterizing and then capturing the steady-state and dynamic behavior of renewable plants and then putting this information in computer models that are used to analyze the BES have mostly been overcome. While work in this area will be ongoing-as is the case for all BES equipment-the industry is at a point where renewable plant technology should no longer be a mystery to transmission system planners and engineers.

Keenan II Wind Plant near Woodward, Oklahoma
Keenan II Wind Plant near Woodward, Oklahoma

The emphasis now will shift to validating models for bulk renewable plants. The approval and forthcoming implementation of NERC Standard MOD-033-1: Steady-State and Dynamic System Model Validation will up the ante on this topic. Set to be implemented on July 1, 2017, the standard aims to “establish consistent validation requirements to facilitate the collection of accurate data and building of planning models to analyze the reliability of the interconnected transmission system.” NERC planning coordinators are required to implement a validation process for which reliability coordinators and transmission operators must provide data on system behavior. In effect, the critical need to compare dynamic model performance to reality will be formalized via standards.

So, what does this mean? Industry experts have recognized for some time that all models must be validated, and this has been done for most bulk system equipment since the early days of computer tools and planning and analysis methods. The standard mandates that planning coordinators create and administer the processes. The language is stronger and clearer than in the previous standards, recognizing that computer models could not adequately explain the realities of major system failures that occurred during some previous system events, such as the August 2003 blackout.

The processes’ shape, form and details as implemented by the planning coordinators are still to be determined. Despite these uncertainties, a couple of things are clear about bulk renewable plants. The first is that monitoring at the point of interconnection (POI) to the BES will become a de-facto requirement. Measurement data that documents the response of the plant to an event or disturbance on the transmission network is essential for model validation, and continuous monitoring is the most effective way to acquire such data.

Secondly, the scope of this effort is huge. There are probably 500 or more individual renewable plants connected to the BES in the U.S. Through the processes mandated by MOD-033-1, each of these plants requires model validation. While many plants may be of similar size and employ the same technology (i.e. wind turbine or power converter), each plant is unique to some degree and the MOD-033-1 standard’s language (as well as the other standards in the NERC MOD family) views plants as individual entities.

FIGURE 5: Arc Flash Warning Label for a Wind Turbine Electrical Enclosure
FIGURE 5: Arc Flash Warning Label for a Wind Turbine Electrical Enclosure

Balance of Plant Studies

Balance of plant studies include system loss evaluation, power flow, voltage and reactive power evaluations. Short circuit and arc flash evaluations study internal plant faults. Temporary and overvoltage evaluations consider ratings for arresters and grounding transformers.

System Loss Evaluation, Powerflow, Voltage and Reactive Power Evaluation

A total accounting of plant auxiliary loads and I2R (power losses) due to current flow is an important economic evaluation for the plant project. Losses may factor into decisions on conductor and transformer sizing. The steady state power flow analysis is performed to determine if the wind plant can be operated to meet the voltage and power factor requirements specified by the interconnect agreement, which is usually to design within voltage limits of 95 percent to 105 percent of the nominal value 0 and power factor limits of +/-95 percent at the POI of the wind plant to the transmission system. If the power flow study reveals that wind turbine compensation packages do not meet the voltage and power factor requirements, then reactive compensation equipment must be specified and installed to meet the stated interconnect requirements.

Short Circuit and Arc Flash Evaluations

The main purpose of short circuit analysis is to determine the available short circuit levels at the buses, the cables within the wind plant collection system and the interconnect switchyard. The short circuit study also is used to specify the equipment ratings such as ampacity withstand, protective relay settings and concentric neutral cable size. Arc flash analysis blends the short circuit analysis with the result of a protection time current curve to determine the incident energy against which an electrical worker must be protected. This study provides information for warning labels (see example in Figure 5) that inform electrical workers of their personal protective equipment (PPE) requirements.

FIGURE 6: Simulated Temporary Overvoltage on a Feeder
FIGURE 6: Simulated Temporary Overvoltage on a Feeder

Transient and Temporary Overvoltage Studies

Transient and temporary overvoltage studies evaluate transient overvoltages caused from energizing capacitor banks, switching operations, fault initiation and clearing operations. The size of grounding transformers or the high speed grounding switches or both, which are used to reduce the temporary overvoltages, are evaluated. A transient simulation package, such as EMTP-RV or PSCAD-EMTDC (two widely used simulation tools), is used for these evaluations. Figure 6 shows an example output of a temporary overvoltage event on a feeder. The insulation coordination study verifies the ratings and locations of the surge arresters to ensure proper insulation coordination. The protective margins for the equipment also are evaluated to ensure safe protective levels against overvoltages during lightning strikes.

Electrical power studies ensure a wind plant’s efficiency and reliability. Interconnection studies and models allow the plant to effectively interconnect with the power grid, maintain power quality and support system voltage requirements. As wind plants have become a significant component of the modern electrical grid, these interconnection requirements have become more significant.


David R. Mueller is a professional engineer and director of energy systems studies at EnerNex. His group has extensive experience in performing power system studies for utility, commercial and industrial clients. They have performed electrical power studies for some of the largest wind plants in U.S., and have worked with many different wind plant developers. Recent projects include offshore projects in the U.S. and Europe. Mr. Mueller is an expert in power quality and a troubleshooter of power problems.

Smart Metering (SM) and Advanced Metering Infrastructure (AMI)

Smart Metering and AMI is a transformational process addressing multiple business and technical needs of the utility enterprise. This is more than just smart meters and communications networks; it includes all of the back end applications that can leverage the meter assets, such as outage notification, demand response, call center optimization, disputed billing process handling, pre-payment opportunities, and service connection management methods and procedures, to name a few.

Implementing SM and AMI faces the same business, engineering, and operational challenges as any other across-the-utility information technology endeavors – most notably risk associated with embracing proprietary technology, missing functionality and early obsolescence. Effective SM and AMI development, implementation, and operation relies on a marriage of electric power engineering with information technology expertise: a key component of EnerNex’s expertise and experience.

EnerNex provides an array of engineering and consulting services geared towards intelligent and effective implementation of SM and AMI. This covers all phases of project development, starting with capturing system requirements where our experts leverage a “Use Case” centric view of activities needed to be accomplished and their interaction with systems and other users. Subsequent project steps typically examine other critical areas, such as: modeling of business cases, building inter-department consensus, assembling and assessing system functional requirements and non-functional requirements, developing a system design, hardware and software specifications and standards, complete procurement services including RFI and RFQ process support, supplier rating system, response evaluation methodology, deployment management, and training of office and field personnel.

Demand Response (DR)

Demand response can be as simple as load interruption directed by the energy supplier in response to severe demand requirements, to complex customer defined load management in response to price signals. DR is one of the components of a “Non-Wires Alternative” that many utilities are effectively using to avoid expensive distribution fortification or upgrade.

 

Often the success and/or failure of demand response programs can be linked to program implementation challenges such as rate/tariff design rate structures communication (e.g. price signals) or ineffective incentives used by utilities to encourage customers to accept operational change. The issues of program design, rate structure and customer impact have a tremendous influence on the success or failure of load management initiatives. Demand response has traditionally been used as a tool of the energy industry to ensure system stability. However, the introduction of microelectronics, communications, home automation and the Internet of Things (IoT) has led to the development of cost effective solutions that have the capability to allow the consumer to take control of managing their energy load and ultimately, the price they pay for energy.

EnerNex has the experience and skills to turn your DR program into a successful operational asset and customer engagement process that can deliver value to all parties.

Energy Assurance Planning

Natural and man-made disasters cause an estimated $57B in average annual costs for all parties; large single events have resulted in losses of $100B or more. Events, such as the World Trade Center disaster, Hurricane Katrina, and most recently Hurricane Helene, have demonstrated an acute need to revisit, revise and implement an effective energy assurance plan. Energy assurance plans assess the functionality and interdependencies of buildings and infrastructure systems and the role they play in sustaining service and rapidly restoring critical services to a community following a hazard event.

 

EnerNex assists our clients in developing comprehensive energy assurance plans that mitigate and minimize the impact of energy disruptions. Our experts assess critical infrastructure risks and evaluate appropriate mitigation strategies and can help in developing an effective business continuity/disaster recovery (BC/DR) plan for utilities and your customers.

Microgrid Development

As the electric grid becomes more distributed and interactive, microgrids are playing an increasingly important role in our energy future. Decision makers at military bases, corporate and institutional campuses, residential communities and critical facilities across the world are exploring and implementing microgrids to meet economic, resiliency and environmental goals. Utility-grade microgrids are being deployed to meet transmission constraints, reliability requirements and safe-havens in the event of a significant storm event.

Microgrid_development Graphic steps to support grid modernization

Bringing together a portfolio of distributed energy resources into a controllable, islandable microgrid comes with its own set of challenges. The key to solving these challenges is in architecting a system to support information exchanges between components across well-defined points of interoperability (interfaces) in a technology independent manner. This interoperability ensures that the system is resilient to technology change. Modern systems engineering techniques must be employed to ensure that individual sub‐systems are clearly identified, their functions enumerated, their data requirements known, and the points of interoperability clearly specified, along with the commensurate monitoring, command and control that is needed to ensure grid stability. With such architecture, we can apply best of breed technology available today to support those information exchanges at interface boundaries but be free to upgrade / change the implementation technology later without causing a ripple effect throughout the system.

Enterprise Architecture

Enterprise Architecture focuses on aligning an organization’s business strategies with its anticipated, desired and planned technology enhancements. Enterprise Architecture provides a framework to cost-effectively transition from a current “as-is” technology to future enterprise-wide technological solutions. An effective Enterprise Architecture program aligns business investments with long-term business strategies while minimizing risk and providing superior technological solutions. EnerNex’s key asset is its highly skilled and experienced staff who are closely connected to both the smart grid and EA standards and practices. We provide clients with the insight necessary to operate a fully functioning smart grid, which is flexible, scalable, and vendor independent.

Grid Modernization Roadmap

Utility companies across the globe are continually modernizing their grid. Each company often has different rationales, objectives and priorities. Frequently, smart grid plans are developed for individual, incremental initiatives, rather than as a part of a whole, intelligent and interoperable infrastructure. Planning may be developed around technology choices rather than business and technical requirements. The result of incremental and flawed planning leads to increased cost and risk, lost opportunities, disconnected expectations and dead ends.

 

EnerNex’s approach to grid modernization roadmap development follows a proven, industry-standard approach to grid modernization planning by collaboratively working with the utility to develop a set of prioritized and time-phased grid modernization initiatives unique to its business strategy and objectives. The roadmap developed is holistic, requirements-based, business value driven and actionable. It often builds on and leverages existing applications and infrastructure, and incorporates industry standards to ensure interoperability, flexibility and reduced cost and risk.

Utility Communications

Utility communication and control systems are increasingly interconnected to each other and to public networks and as a result, they are becoming increasingly more susceptible to disruptions and cyber attacks. EnerNex has experience with the various issues relating to development, implementation and optimization including feasibility analysis, design, software development and customization, project management and acceptance. Our expertise extends from being involved in the development of the fundamental standards that support utility communication and automation, through deployment and securing of those resources. EnerNex personnel were heavily involved in development of such standards and protocols as IEC 61850, IEC 60870-5 and DNp3. Our staff played a key role in the EPRI Utility Communication Architecture (UCA) project and the IntelliGrid Architecture effort.

Related Articles

Related

Grid Modernization & Grid Architecture

Helping our clients implement and integrate grid modernization technologies and processes that are aligned with tomorrow’s utility. A Grid Modernization program frequently includes many complex utility engineering and operational topics, many times the scope of these...

read more

Grid Modernization with Artificial Intelligence

_______________________________________________________________________________________________________________________ Introduction The electric power industry is undergoing a transformative era, driven by digitalization, renewable energy integration, and increasing...

read more
X